Document Version: 1.0 Date: August 8, 2025 Author: CrownThrive, LLC — [email protected] Project: CHLOM™ — Compliance Hybrid Licensing & Ownership Model
1. Objective
Establish the high-level testing methodology and deployment strategy for DAL, ensuring secure, stable, and compliant rollout across environments. Phase 0 focuses on designing test plans, staging workflows, and rollback contingencies for integration with DLA, LEX, and external systems.
2. Testing Stages
- Unit Testing
- Validate smart contract logic modules (payout, escrow, compliance checks).
- Mock API endpoints for license verification, identity checks, and ZK-proof retrieval.
- Integration Testing
- End-to-end verification between DAL, DLA, and LEX APIs.
- Compliance AI and Fingerprint ID/DID resolution simulation.
- Performance Testing
- Throughput and latency benchmarks under peak transaction load.
- Stress testing for batch payout processing.
- Security Testing
- Smart contract vulnerability scans.
- Penetration testing for API endpoints.
- Governance Testing
- DAO-triggered actions, dispute resolutions, and escalation flows.
3. Deployment Pipeline
- Development Environment — Build and run initial unit tests.
- Testnet/Staging Environment — Deploy smart contracts and APIs for integration and load testing.
- Audit Phase — Third-party contract and security reviews.
- Pre-Production Review — Governance sign-off and compliance verification.
- Mainnet Deployment — Controlled rollout with staged activation.
- Post-Deployment Monitoring — Continuous logging and anomaly detection.
4. Rollback Procedures
- Smart Contracts
- Use proxy upgrade pattern for reversions.
- Emergency pause function for payout halt.
- APIs
- Blue-green deployment to switch between stable and rollback versions.
- Data Integrity
- Backup CHLOM Ledger entries and off-chain compliance proofs.
5. Monitoring Post-Deployment
- Real-time payout flow monitoring with automated alerts.
- Compliance verification on random payout samples.
- Performance trend analysis for scaling readiness.
6. Example Deployment Script (Pseudo Bash)
#!/bin/bash
# Deploy DAL smart contracts to testnet
truffle migrate --network testnet
# Run post-deployment tests
npm run test:integration
# Notify governance panel
curl -X POST https://dao.chlom.io/notify --data '{"deployment":"complete"}'
7. Phase Allocation
- Phase 0 — Define test and deployment strategy, including rollback plans.
- Phase 1 — Implement automated test suites and staging workflows.
- Phase 2 — Integrate security scanning and audit processes.
- Phase 3 — Conduct full-scale governance and performance tests.
- Phase 4 — Execute mainnet deployment with staged activation.
- Phase 5 — Continuous improvement and scaling optimization.
Next Step: Proceed to Phase 4–5 Launch Plan & Governance Transition for DAL to define full-scale rollout, DAO oversight activation, and long-term operational scaling.